|
|
|
|
|
|
|
|
|
|
Contents
Breaches of Action
and Limit Levels for Air Quality
Breaches of Action and Limit Levels
for Noise
Breaches of Action and Limit Levels
for Water Quality
Soft Shore Ecological Monitoring
1.4 SUMMARY OF CONSTRUCTION WORKS
1.5 SUMMARY OF EM&A PROGRAMME
REQUIREMENTS
1.6 STATUS OF STATUTORY ENVIRONMENTAL
COMPLIANCE WITH THE ENVIRONMENTAL PERMIT
2.1.1 Monitoring Requirements and
Equipment
2.1.2 Monitoring Schedule for the
Reporting Month
2.1.3 Results and Observations
2.2.1 Monitoring Requirements and
Equipment
2.2.2 Monitoring Schedule for the
Reporting Month
2.2.3 Results and Observations
2.4 COMPENSATION WOODLAND MONITORING
2.5 PRESERVED/TRANSPLANTED PLANT SPECIES
OF CONSERVATION IMPORTANCE MONITORING
2.5.1 Preserved Plant Species of
Conservation Importance
2.5.2 Transplanted Plant Species of
Conservation Importance
2.7 Soft Shore Ecological Monitoring
2.10 LANDSCAPE AND VISUAL MONITORING
2.11 IMPLEMENTATION STATUS OF ENVIRONMENTAL MITIGATION
MEASURES
2.12 SUMMARY OF COMPLAINTS, NOTIFICATION OF
SUMMONS AND SUCCESSFUL PROSECUTIONS
ANNEX b Environmental Mitigation Implementation Schedule
ANNEX c Status of Submissions and Implementation Status of
Mitigation Measures under EP
ANNEX d Status of Statutory Environmental Requiremens
ANNEX e1 Calibration Certificates for Air Quality
ANNEX e2 Monitoring Schedule for Air Quality
ANNEX e3 Monitoring Results for Air Quality
ANNEX e4 Event and Action Plan for Air
Quality
ANNEX f1 Calibration Certificates for Noise
ANNEX f2 Monitoring Schedule for Noise
ANNEX f3 Monitoring Results for Noise
ANNEX f4 Event and Action Plan for Noise
ANNEX g Compensation Woodland Monitoring
ANNEX h Preserved/Transplanted Plant Species of Conservation
Importance Monitoring
ANNEX h1 Preserved Plant Species of Conservation Importance
ANNEX I Eco-shoreline Monitoring
ANNEX J Landscape and Visual Monitoring
ANNEX J1 Examples of Landscape and Visual Mitigation Measures
ANNEX J2 Event and Action Plan for Landscape and Visual Mitigation
Measures
ANNEX L Monitoring Schedule for the Next
Reporting Period
List of Tables
Table 1.1 Contact Information of Key
Personnel
Table 1.2 Major Activities in the Reporting
Period
Table 1.3 Summary of Status for the
Environmental Aspects under the Updated EM&A Manual
Table 2.1 Action and Limit Levels for 1-hour
TSP
Table 2.2 Air Quality Monitoring Details
Table 2.3 Summary of 1-hour TSP Monitoring
Results in the Reporting Period
Table 2.4 Action and Limit Levels for
Construction Noise
Table 2.5 Noise Monitoring Details
Table 2.6 Summary of Construction Noise
Monitoring Results in the Reporting Period
Table 2.7 Key Observations Identified during
the Site Inspection in this Reporting Month
Table
2.8 Quantities
of Different Waste Generated and Imported Fill Materials
Table 2.9 Implementation Status of Landscape
and Visual Mitigation Measures
|
LIST OF FIGURES |
|
Acronyms and abreviations
|
Acronyms |
Description |
|
C&D |
Construction and Demolition |
|
CAP |
Contamination Assessment Plan |
|
CEDD |
Civil Engineering and Development Department |
|
CWD |
Chinese White Dolphin |
|
DCM |
Deep Cement Mixing |
|
DO |
Dissolved Oxygen |
|
EIA |
Environmental Impact
Assessment |
|
EIAO |
Environmental Impact Assessment Ordinance |
|
EIS |
Ecologically Important Stream |
|
EM&A |
Environmental Monitoring and Audit |
|
EP |
Environmental Permit |
|
EPD |
Environmental
Protection Department |
|
ER |
Engineer's Representative |
|
ERM |
ERM-Hong Kong, Limited |
|
ET |
Environmental Team |
|
HVS |
High Volume Sampler |
|
IEC |
Independent Environmental
Checker |
|
PDA |
Planned Development Area |
|
PME |
Powered Mechanical Equipment |
|
QPME |
Quality Powered Mechanical Equipment |
|
RAP |
Remediation Action Plan |
|
RR |
Remediation Report |
|
RTTM |
Real Time Tracking and
Monitoring |
|
SS |
Suspended Solid |
|
TCB |
Tung Chung Bay |
|
TCE |
Tung Chung East |
|
TCNTE |
Tung Chung New Town Extension |
|
TCW |
Tung Chung West |
|
The Project |
Tung Chung New Town Extension
(East) |
|
THW |
Tai Ho Wan |
|
TSP |
Total Suspended Particulate |
|
TUE |
Tung Chung Line Extension |
|
Updated EM&A Manual |
Updated Environmental Monitoring and Audit Manual for
Tung Chung New Town Extension prepared by ERM under Agreement No. CE 60/2017
(EP) and deposited to EPD under Environmental Permit No. EP-519/2016 |
Tung Chung New Town
Extension (TCNTE) is one of the major initiatives under the Government's
multi-pronged approach to increase land supply to meet Hong Kong's medium- to
long-term needs for housing, economic and social developments. The Environmental Impact Assessment (EIA)
Report for TCNTE (Register No. AEIAR-196/2016) was approved on 8 April 2016 and
the Environmental Permit (EP) No. EP-519/2016, covering the construction and
operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP cover both Tung Chung
East (TCE) and Tung Chung West (TCW).
ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role of
Environmental Team (ET) for the construction and operation of TCE Project (“the
Project”) in accordance with the requirements specified in the EP, Updated
Environmental Monitoring and Audit (EM&A) Manual, EIA Report of the TCNTE
project and other relevant statutory requirements.
The
construction of the Contract No. NL/2017/03 - Tung
Chung New Town Extension – Reclamation and Advance Works (“Contract 1”) at TCE commenced
on 9 July 2018 and was completed on 8 September 2025.
The
construction of the Contract No. NL/2020/02 - Tung Chung New Town
Extension – Salt Water Supply System (“Contract 2”) at
TCE commenced
on 4 September 2021.
The
construction of the Contract No. NL/2020/03 - Tung Chung New Town
Extension – Major Infrastructure Works in Tung Chung East (“Contract 3”) at TCE
commenced on 5
November 2021.
The construction of the Contract No. NL/2020/07 -
Tung Chung New Town Extension – Tai Ho Interchange (“Contract 7”) at TCE
commenced on 15 March 2022.
The works area in Area 113 has been handed overed
to MTRC since 24 March 2025. The
corresponding environmental monitoring, site inspection, environmental
complaint handling and EM&A reporting in the above-mentioned works area
will be covered by EM&A programme of TUE and
carried out by existing ET and IEC of TUE.
This is the Monthly EM&A report presenting the EM&A works carried out during the period from 1 to 31 July 2026 for the TCE Project in accordance with the Updated EM&A Manual.
A summary of monitoring and audit activities conducted in the reporting period is listed below:
Air Quality Monitoring 5 sessions
Noise Monitoring 5 sessions
Preserved Plant Species
Monitoring 1
session
Environmental Site Inspection
· Contract 2 5 sessions
· Contract 3 5 sessions
· Contract 7 4 sessions
Environmental Management Meeting
· Contract 2 1 session
· Contract 3 1 session
· Contract 7 1 session
Environmental auditing works, including weekly site inspections of construction works conducted by the ET, audit of implementation of Complaint Management Plan, Detailed Preservation and/or Translocation of Plant Species of Conservation Importance, and Waste Management Plan were conducted in the reporting period. Based on the audit results and the observation for the reporting period, environmental pollution control and mitigation measures for the Project were properly implemented.
No exceedance of Action and Limit Levels was recorded for construction air quality monitoring in the reporting period.
No exceedance of Action and Limit Level was recorded for construction noise monitoring in the reporting period.
Water quality monitoring was suspended in the reporting period.
The construction of vertical eco-shoreline, mangrove eco-shoreline and rocky eco-shoreline has been substantially completed. Eco-shoreline monitoring was scheduled during the reporting period.
There was no notification of summons or prosecution recorded in the reporting period.
No environmental complaint was received in the reporting period. The environmental complaint handling and EM&A reporting in the temporary works area in Area 113 used by MTRC will be covered by EM&A programme of TUE and carried out by existing ET and IEC of TUE.
There was no reporting change in the reporting period.
Potential environmental impacts arising from the upcoming construction activities in the next reporting period of August 2026 are mainly associated with dust emission, noise from plant operation during normal working hours and restricted hours, handling and storage of C&D materials generated from construction activities, efficiency of wastewater and drainage management and tree protection. The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures. The ET will also recommend to the Contractor about the environmental toolbox topics on the abovementioned key issues for the coming month.
Tung Chung New Town Extension (TCNTE) is one of the major initiatives under the Government's multi-pronged approach to increase land supply to meet Hong Kong's medium- to long-term needs for housing, economic and social developments. The Environmental Impact Assessment (EIA) Report for TCNTE (Register No. AEIAR-196/2016) was approved on 8 April 2016 and the Environmental Permit (EP) No. EP-519/2016, covering the construction and operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP cover both Tung Chung East (TCE) and Tung Chung West (TCW).
ERM-Hong Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team (ET) for the construction and operation of TCE Project (“the Project”) in accordance with the requirements specified in the EP, Updated Environmental Monitoring and Audit (EM&A) Manual ([1]), EIA Report of the TCNTE project ([2]) and other relevant statutory requirements.
The TCNTE comprises the following elements:
(a) TCE Project
1. Reclamation of the
seabed by a non-dredged method at TCE to form a total of about 130 hectares of
land;
2. Construction of
about 4.9 kilometers of seawalls, with an
eco-shoreline, three drainage box culvert outfalls, three circulation drains
and a seawater intake at TCE;
3. Provision of
infrastructure for Tung Chung Area 58, including construction of a single two-lane
road with a footpath and the associated utility works;
4. Construction of
proposed open space;
5. Construction of
roads, footpaths, cycle tracks and the associated junction / road improvement works;
6. Engineering
infrastructure works covering drainage, sewerage, waterworks (including a fresh water service reservoir, a salt
water service reservoir and a salt water
pumping station), common utility tunnels and landscaping works; and
7. Implementation of environmental
mitigation measures and environmental monitoring and audit programme for the
works.
(b) TCW Project
1. Site formation works at TCW;
2. Construction of proposed open space;
3. Construction of the River Park including a visitor centre at TCW; and
4. Construction of sustainable urban drainage systems at TCW.
The locations of Contracts 1, 2, 3 and 7 are shown in Figure 1.1 to 1.4. The construction and the reclamation related marine works of Contract 1 commenced on 9 and 13 July 2018, respectively and was completed on 8 September 2025. The construction of Contracts 2, 3 and 7 commenced on 4 September 2021, 5 November 2021 and 15 March 2022, respectively.
This is the Monthly EM&A Report for the TCE Project which summarises the key findings of the EM&A programme during the reporting period from 1 to 31 July 2026 for the construction works.
The organization structure of the Project is shown in Annex A. The key personnel contact names and contact details are summarized in Table 1.1 below.
Table 1.1 Contact Information of Key Personnel
|
Party |
Position |
Name |
Telephone |
|
Environmental Team (ET) (ERM-Hong Kong, Limited) |
ET Leader |
Kelvin So |
3894 9504 |
|
Deputy ET Leader |
Raymond Chow |
2271 3281 |
|
|
Independent Environmental Checker (IEC) (Binnies Hong Kong Limited) |
IEC |
Manuel Chua |
3894 9807 |
|
Deputy IEC |
Edward Lau |
3894 9695 |
|
|
Contract No.
NL/2020/02 - Tung Chung New Town Extension – Salt Water
Supply System (Contract 2) |
|||
|
Civil Engineering and Development Department |
Senior Engineer |
Patrick C Y Yeung |
2231 4435 |
|
Electrical & Mechanical Engineer |
Miki S Y Chung |
3894 9524 |
|
|
Engineer’s Representative (ER) (AECOM Asia Company Limited) |
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
|
Senior Resident Engineer |
Sunny Ng |
3894 9605 |
|
|
Senior Resident Engineer |
Vincent Leung |
3894 9645 |
|
|
Resident Engineer |
Amen Fung |
3894 9676 |
|
|
Senior Inspector of Works |
Lai Kwok Wai |
3894 9731 |
|
|
Contractor (China Geo-Engineering Corporation) |
Construction Manager |
Ambrose Kwong |
6198 7787 |
|
Site Agent |
Patrick Lam |
9227 9872 |
|
|
Construction Team Leader |
Edward Mok |
6498 4306 |
|
|
Environmental Officer |
Fung Ka Bao |
9120 1489 |
|
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
|
Contract No. NL/2020/03 - Tung Chung New Town Extension
– Major Infrastructure Works in Tung Chung East (Contract 3) |
|||
|
Civil Engineering and Development Department |
Senior Engineer |
Phoebe Tang |
2231 4423 |
|
Senior Engineer |
Colin K C Wong |
2231 4417 |
|
|
Engineer |
Timothy H M Chan |
2231 4473 |
|
|
Engineer |
Wing Chen |
3894 9704 |
|
|
Engineer’s Representative (ER) (AECOM Asia Company Limited) |
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
|
Chief Resident Engineer |
Gloria Tang |
3894 9639 |
|
|
Senior Resident Engineer |
Winston Wong |
3894 9650 |
|
|
Resident Engineer |
Marcus Choi |
3894 9649 |
|
|
Resident Engineer |
Anson Yip |
3894 9559 |
|
|
Senior Inspector of Works |
Douglas Ng |
3894 9737 |
|
|
Contractor (Build King Civil Engineering Limited) |
Construction Manager |
Paul Lui |
9095 7922 |
|
Senior Site Agent |
Aldous Lo |
9225 0368 |
|
|
Site Agent |
Kwong Po Hang |
9283 6844 |
|
|
Construction Team Leader |
Qiu Da |
5938 8793 |
|
|
Environmental Officer |
Tim Lin |
6390 0018 |
|
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
|
Contract No. NL/2020/07 - Tung Chung New Town Extension
– Tai Ho Interchange (Contract 7) |
|||
|
Civil Engineering and Development Department |
Senior Engineer |
Phoebe Tang |
2231 4423 |
|
Engineer |
S H Leung |
2231 4449 |
|
|
Engineer’s Representative (ER) (AECOM Asia Company Limited) |
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
|
Senior Resident Engineer |
Kelvin Kwan |
3894 9641 |
|
|
Resident Engineer |
Kingsley Ho |
3894 9552 |
|
|
Resident Engineer |
Jessie Tang |
3894 9678 |
|
|
Senior Inspector of Works |
C K Liu |
3894 9733 |
|
|
Contractor (Build King Civil Engineering Limited) |
Site Agent |
Vincent Kwan |
9833 1313 |
|
Deputy Site Agent |
Andy Chung |
9878 0870 |
|
|
Construction Team Leader |
Vincent Lo |
9883 9229 |
|
|
Environmental Officer |
Nash Wong |
9810 1946 |
|
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
As informed by the Contractor, details of the major works carried out in this reporting period are listed below:
Table 1.2 Major Activities in the Reporting Period
|
Activities |
Key Issues |
Key Mitigation Measures |
|
Contract No. NL/2020/02 - Tung Chung New Town
Extension – Salt Water Supply System (Contract 2) |
||
|
Land-based
Works |
||
|
· Construction of fence wall for pumping station at Portion 6 · Slope works, road and drain works for SWSR at Portion 3 · Remedial and Outstanding Works of SWSR at Portion 3 · Overall CCTV survey on new laid watermain |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
|
Contract No. NL/2020/03 - Tung
Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
|
Land-based Works |
||
|
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 and 3 structure · UU laying works in CUT 1,2,3 · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L5, L7, L8, L9, D4 and D5 and Portion 16 · DCS works at Road L5, D4 and L7. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road works in Road L3, L4 and L5 · Road widening works at Ying Hei Road · ELS for SIBC construction · Construction for BC3 at Portion 22B · Pipe pile installation at underpass D1 |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management |
|
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
|
Land-based Works |
||
|
· Final pressure test for rising mains at Portion 146-1 to 146-11 · Road and Drainage works at SR-A1 to A5 at Portion 31 · Drainages works at Portion 146-3 · Smart lamp poles ducting laying and footings at Road P1 footpath at 146-3, 146-6, 146-7 and 146-11 · Formation for Road P1 footpath and cycle track at 146-1, 146-3, 146-6, 146-7, and 146-11 · Irrigation pipes at P1 road · Smart Lamp poles at P1 road · Backfilling soil mix at P1 road dwarf wall · Pak Mong Bridge insitu deck and furniture · Roads reinstatement at Portion 32 Depot section · RC works and drainage works at SR6 eastbound near Wall D · Parapet Transition construction at RW-R7, A1 and A2 · Parapet construction RW-R5 and Wall D Bay · Road works at Bridge C and Approaching Box Structures · Earthworks casting yard A2 · Asphalt paving, kerbs and concrete profile barriers installation for Road P1 at 146-1, 146-3 · Site clearance within site boundary |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The environmental mitigation implementation schedule is presented in Annex B.
The status for all environmental aspects is presented in Table 1.3. The EM&A requirements remained unchanged during the reporting period.
Table 1.3 Summary of Status for the Environmental
Aspects under the Updated EM&A Manual
|
Parameters |
Status |
|
|
Air Quality |
||
|
Baseline Monitoring |
The results of baseline air quality monitoring for
TCE were reported in Baseline Monitoring Report and submitted to EPD under EP
Condition 3.4 |
|
|
Impact Monitoring |
On-going for TCE, monitoring conducted three times
every six days |
|
|
Noise |
|
|
|
Baseline Monitoring |
The results of baseline noise monitoring for TCE
were reported in Baseline Monitoring Report and submitted to EPD under EP
Condition 3.4 |
|
|
Impact Monitoring |
On-going for TCE, monitoring conducted once per week |
|
|
Impact Monitoring for Road Traffic Noise during
Operational Phase |
To be conducted during operational phase |
|
|
Fixed Noise Commissioning Test |
Under implementation by the Contractor of Contract 3 |
|
|
Water Quality |
|
|
|
Baseline Monitoring |
The results of baseline water quality monitoring for
TCE were reported in Baseline Monitoring Report and submitted to EPD under EP
Condition 3.4 |
|
|
Impact Monitoring |
Suspended for TCE with approval from EPD |
|
|
Waste
Management |
|
|
|
Waste Monitoring |
On-going |
|
|
Land
Contamination |
|
|
|
Contamination Assessment Plan (CAP), Remediation
Action Plan (RAP) and Remediation Report (RR) |
To be conducted under TCW. Refer to the EM&A
Reports of TCW. |
|
|
Ecology |
|
|
|
Monitoring for Compensation Woodland |
Compensation Woodland Planting was completed on 30
September 2022. On-going, monitoring conducted quarterly. The handover for woodland compensation from Contact
No. NL/2020/C2 to Contract No. NL/2020/03 was conducted on 12 June 2025. Quarterly post-planting monitoring report
was submitted to EPD on 8 May 2026. |
|
|
Monitoring for Emergent Plant inside the future
River Park |
To be conducted under TCW. Refer to the EM&A
Reports of TCW. |
|
|
Monitoring for Translocated Amphibians of
Conservation Importance |
To be conducted under TCW. Refer to the EM&A
Reports of TCW. |
|
|
Monitoring for Preserved/Transplanted Plant Species
of Conservation Importance |
On-going, for preserved plant species, monitoring
conducted once per month; for transplanted plant species, replacement
planting was carried out on 28 April 2023 and 19 September 2023. Monitoring conducted once per month for the
first year, and quarterly from second year onwards until land handover |
|
|
Monitoring for Tung Chung Stream EIS and Wong Lung
Hang EIS |
To be conducted under TCW. Refer to the EM&A
Reports of TCW. Monitoring for Wong
Lung Hang was not required and the proposal was accepted by EPD on 2
September 2021 |
|
|
Eco-shoreline Monitoring |
Third year wet season monitoring was conducted on 6,
15 and 16 July 2026. The third year dry season monitoring report was submitted to
AFCD and EPD on 3 June 2026. |
|
|
Tung Chung Bay and Tai Ho Wan Baseline Monitoring |
The results of baseline soft shore ecological
monitoring at Tung Chung Bay and Tai Ho Wan were reported in Baseline
Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
|
Tung Chung Bay and Tai Ho Wan Impact Monitoring |
Completed |
|
|
Tung Chung Bay and Tai Ho Wan Post-construction Monitoring |
Completed |
|
|
Landscape and
Visual |
|
|
|
Baseline Monitoring |
The results of baseline landscape and visual
monitoring were reported in Baseline Monitoring Report and submitted to EPD
under EP Condition 3.4 |
|
|
Impact Monitoring |
On-going |
|
|
Site
Environmental Audit |
|
|
|
Regular Site Inspection |
On-going |
|
|
Dolphin Watching Plan implementation measures |
Completed |
|
|
Works Vessel Travel Route Plan implementation
measures |
Completed |
|
|
Silt Curtain Deployment Plan implementation measures |
All silt curtain was
removed in accordance with the Silt Curtain Deployment Plan and after
obtaining the acceptance from EPD |
|
|
Spill Response Plan implementation measures |
Completed |
|
|
Detailed Preservation and/or Translocation Plan for
Plant Species of Conservation Importance implementation measures |
Under implementation by the Contractor of Contract 2 |
|
|
Detailed Compensatory Woodland
Planting Plan implementation measures |
Under implementation by the Contractor of Contract 3 |
|
|
Waste Management Plan implementation measures |
Under implementation by the Contractor of Contract
2, 3 and 7 |
|
|
Complaint Hotline and Email Channel |
Under implementation by the Contractor of Contract
2, 3 and 7 |
|
|
Environmental Log Book |
On-going |
|
Taking into account the construction works, impact monitoring of air quality, noise and waste management were carried out in the reporting period. The monitoring schedule of air quality and noise are provided in Annex E2 and Annex F2 respectively.
The EM&A programme also involved environmental site inspections and related auditing conducted by the ET for checking the implementation of the required environmental mitigation measures recommended in the approved EIA Report and relevant EP submissions, including Complaint Management Plan, Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance, and Waste Management Plan.
To promote the environmental awareness and enhance the environmental performance of the contractors, environmental trainings and regular environmental management meetings were conducted during the reporting period, which are summarized as below:
• Three (3) environmental management committee meetings were held among the relevant contractors, ER, ET, IEC and CEDD on 15 July 2026 (for Contract 2), 22 July 2026 (for Contract 3) and 14 July 2026 (for Contract 7);
• Environmental toolbox trainings on removal of stagnant water and preventation of mosquito breeding, waste collection, handling and disposal on 7 and 21 July 2026 were conducted for Contract 2;
• Environmental toolbox trainings on construction dust and suppression, construction noise and suppression, wastewater handling, discharge and treatment facilities, waste collection, handling and disposal, site plant and machinery (operation and maintenance), maintenance of site access, site boundary and haul roads, handling and storage of chemical, anti-mosquito control measures, chemical waste and handling of chemical spillage on 2, 7, 9, 14, 16, 21, 23, 28 and 30 July 2026 were conducted for Contract 3;
• Environmental toolbox trainings on loading, unloading and transfer of materials, stockpiling, backfilling, deposition and compaction of fill material, scaffolding on 8, 15, 22 and 29 July 2026 were conducted for Contract 7.
The status of statutory environmental compliance with the EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures are presented in Annex C.
The environmental licenses and permits, including environmental permit, discharge license under Water Pollution Control Ordinance, registration as chemical waste producer, construction noise permit and specified processes license, which were valid in the reporting period are presented in Annex D. No non-compliance with environmental statutory requirements was recorded.
The works area in Area 113 has been handed over to MTRC since 24 March 2025. The corresponding environmental monitoring, site inspection, environmental complaint handling and EM&A reporting in the above-mentioned works area will be covered by EM&A programme of TUE and carried out by existing ET and IEC of TUE.
According to the Updated EM&A Manual of the Project, impact air quality monitoring in terms of 1-hour Total Suspended Particulate (TSP) was conducted three (3) times every six (6) days when the highest dust impact was expected. The Action and Limit Levels of the air quality monitoring is provided in Table 2.1 below.
Table 2.1 Action and Limit Levels for 1-hour TSP
|
Location |
Action Level (µg/m3) |
Limit Level (µg/m3) |
|
Monitoring station for Tung Chung East |
279 |
500 |
Portable direct reading dust meters were used to measure 1-hour TSP levels in undertaking the air quality monitoring for the Project. The proposed use of portable direct reading dust meters was submitted to IEC and obtained agreement from the IEC as stated in Section 5.5 of the Updated EM&A Manual. With the use of direct reading dust meter, it can allow prompt and direct results for the EM&A reporting and the implementation of the event and action plan. The portable direct reading dust meter would be calibrated every year against High Volume Sampler (HVS) to check the validity and accuracy of the results measured by direct reading method.
The
monitoring location and equipment used in the impact air quality monitoring programme are summarized in Table 2.2 and illustrated in Figure 2.1. Copies of the calibration certificates for
the equipment are presented in Annex
E1, which showed that
the portable direct reading dust meter is capable of
providing comparable results with that provided by a
HVS.
Table 2.2 Air Quality Monitoring Details
|
Monitoring Station |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
|
DM-1 |
Tung Chung Area 56 – Ying Tung Estate |
1-hour TSP |
Three times per six days during the construction period of the Project |
3, 9, 15, 21, and 27 July 2026 |
1-hour TSP Dust Meter SIBATA LD-5R (S/N: 781281) |
Note: It should be noted that
impact monitoring at other construction dust monitoring locations at TCE as
stated in the Updated EM&A Manual will commence after the flat intake (for
Monitoring Stations DM-2, DM-3 and DM-4).
The schedule for air quality monitoring during the reporting period is provided in Annex E2.
The monitoring results for 1-hour TSP are summarized in Table 2.3. The monitoring data and the graphical presentation are provided in Annex E3.
Table 2.3 Summary of 1-hour TSP Monitoring Results in the Reporting Period
|
Monitoring Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
|
DM-1 |
36 |
24-48 |
279 |
500 |
Major dust sources in the reporting period included haul road traffic and excavation under the Project and nearby construction sites.
No exceedance of Action and Limit Levels was recorded for construction air quality monitoring in the reporting period. No action was thus required to be undertaken in accordance with the Event and Action Plan presented in Annex E4.
According to the Updated EM&A Manual of the Project, impact noise monitoring was conducted once per week during the construction phase of the Project. The Action and Limit Level for construction noise of the Project is provided in Table 2.4 below.
Table 2.4 Action and Limit Levels for Construction Noise
|
Time Period |
Action Level |
Limit Level |
|
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A) a, b |
Note:
a Limit level is exceeded when Leq ≥ 75 dB(A). If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
b Reduce to 70 dB (A) for schools and
65 dB (A) during school examination periods.
Noise monitoring was performed using sound level meter at the designated monitoring stations NMS-CA-1A ([3]) ([4]) and NMS-CA-4 (Figure 2.2; Table 2.5) in accordance with the requirements stipulated in the Updated EM&A Manual. Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level. Details of the deployed equipment are provided in Table 2.5. Copies of the calibration certificates for the equipment are presented in Annex F1.
Table 2.5 Noise Monitoring Details
|
Monitoring Station a |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
|
NMS-CA-1A b |
Residential premise in Tung Chung East – Century Link/Ying Hong Road c |
30-minute measurement between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded. |
Once per week for 30 mins during the construction period of the Project |
3,
9, 15, 21, and 27 July 2026 |
Sound Level Meter: Rion NL-52 (S/N: 00175561) Acoustic
Calibrator: LARSON DAVIS CAL200 (S/N: 11334) |
|
NMS-CA-4 |
Residential premise in the reclamation area next to Tung Chung East – Ying Tung Estate |
Note:
a It
should be noted that impact monitoring at other construction noise monitoring
locations at TCE as stated in the Updated EM&A Manual will commence after
the flat intake of residential premise in TCE (for Monitoring Station NMS-CA-1)
and operation of schools (for Monitoring Stations NMS-CA-2 and NMS-CA-3).
b Impact monitoring at
monitoring station NMS-CA-1A commenced on 19 September 2018 in view of the
close vicinity of the construction works near the residential area at Century
Link.
c Due to land handover issue,
NMS-CA-1A was relocated to Ying Hong Road which is located 60m away from the
original location. Proposal on the
relocation of NMS-CA-1A was approved by IEC on 23 November 2018. Noise monitoring at the relocated location
commenced since 24 November 2018.
The schedule for noise monitoring during the reporting period is provided in Annex F2.
Results for noise monitoring are summarized in Table 2.6. The monitoring data and the graphical presentation are provided in Annex F3.
Table 2.6 Summary of Construction Noise Monitoring Results in the Reporting Period
|
Monitoring Station |
Average,
dB(A), |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq (30mins) |
|
NMS-CA-1A |
66.7 |
66.1-67.4 |
75 |
|
NMS-CA-4 |
67.7 |
67.0-68.9 |
75 |
Major noise sources during the noise monitoring included noise from plant operation, craning, haul road traffic, nearby traffic and aircraft as well as nearby construction sites.
No exceedance of Action and Limit Levels was recorded for construction air quality monitoring in the reporting period. No action was thus required to be undertaken in accordance with the Event and Action Plan presented in Annex F4.
No monitoring event for impact water quality monitoring was conducted at all designated monitoring stations during the reporting period. Water quality monitoring has been suspended since 3 October 2023 as all reclamation works and marine construction activities have been completed.
Compensation woodland planting under Contract 2 was completed on 30 September 2022. With the approval from EPD on the monitoring proposal in August 2023, quarterly post-planting monitoring for compensation woodland was commenced in September 2023. Quarterly post-planting monitoring report was submitted to EPD on 8 May 2026. No quarterly post-planting monitoring for the compensation woodland was carried out in the reporting period([5]). Photographic record of the compensation woodland planting is provided in Annex G.
Plant species of conservation importance, including three individuals of Aquilaria sinensis and 33 individuals of Gmelina chinensis, were identified within works areas for Contract 2 during the survey conducted in August 2021. All individuals of Aquilaria sinensis and 31 individuals of Gmelina chinensis were recommended being preserved in-situ while two individuals of Gmelina chinensis (RT-07 and RT-08) were recommended being transplanted to the receptor site in accordance with the Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance approved under Condition 2.21 of EP-519/2016.
Initial tree
survey was conducted in September 2021 under Contract No. NL/2020/02 before the
commencement of construction works. According to the initial
tree survey conducted, the in-situ
preserved plant species of conservation importance of which one individual of Aquilaria sinensis and six individuals
of Gmelina chinensis were found
missing.
During the monthly monitoring of the in-situ
preserved plant species of conservation importance in November 2023, one
individual of Aquilaria sinensis and one individual of Enkianthus quinqueflorus
were newly observed and recommended being preserved in-situ. Registration and measurement for two
additional trees were conducted on 4 December 2023.
Monthly monitoring of the in-situ preserved plant species of conservation importance by the Qualified Personnel (QP) appointed under Contract 2 was implemented in the reporting period. Health condition was considered fair for the majority of the in-situ preserved plant species of conservation importance, of which two individuals of Gmelina chinensis could not be monitored as a result of unsafe access to the locations, as recorded during the monitoring carried out on 29 July 2026.
Tree protection zones for the in-situ preserved plant species of conservation importance were demarcated. No injuries and/or damages to the individuals of the in-situ preserved plant species of conservation importance were reported by the QP since the previous monitoring events. Photographic record and tree schedule of the preserved plant species of conservation importance monitoring are provided in Annex H1.
The ET will continue to monitor the implementation of monitoring of in-situ preserved plant species of conservation importance.
Site visit to the receptor site for the transplanted plant species of conservation importance under Contract 2 was carried out on 20 January 2022 prior to the commencement of transplantation works for the transplanted plant species of conservation importance on 21 January 2022.
The transplanted plant species of conservation importance were both certified as dead trees by the QP on 15 June 2022 as no living signs were observed. Replacement planting of new trees of the same species, or other species to the satisfaction of the Project Manager, at the Contractors’ expense would be deemed necessary in accordance with the conditions under the approved Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance. Replacement planting of three (3) Aquilaria sinensis were completed on 28 April 2023. One (1) individual was certified dead by the QP as no living signs were observed on 26 July 2023. The removal of the dead tree and replanting of one (1) individual of Aquilaria sinensis were completed on 19 September 2023.
The establishment period of two (2) individuals of Aquilaria sinensis was ended on 27 April 2024 and one (1) individual of Aquilaria sinensis was ended on 18 September 2024.
Monitoring of the replacement planting will be conducted once per month for the first year, and quarterly from second year onwards until land handover. No quarterly monitoring of three (3) individuals of Aquilaria sinensis were scheduled during the reporting period.
ET will
continue to monitor the implementation of monitoring of in-situ preserved/
transplanted plant species of conservation importance.
The construction of vertical eco-shoreline, mangrove eco-shoreline and rocky eco-shoreline has been substantially completed. Photographic record is provided in Annex I.
The third year dry season monitoring and annual report were submitted to AFCD and EPD on 3 June 2026.
Third year wet season monitoring of ichthyoplankton was conducted using plankton net on 6 July 2026 while monitoring of juvenile fish was conducted using purse seine on 15 and 16 July 2026. Monitoring is conducted for at least 3 years after the completion of eco-shoreline, twice in wet season and twice in dry season, while ichthyoplankton and juvenile fish monitoring will be conducted on a monthly basis covering May to August for at least 3 years, in order to determine the effectiveness of the eco-shoreline in accordance with the Updated EM&A Manual and Eco-shoreline Implementation Plan.
The post-construction soft shore ecological monitoring has been
conducted for 2 years since the completion of construction. As no significant changes in density or the distribution
pattern of horseshoe crab, seagrass and intertidal soft shore communities were
observed throughout the construction and post-construction phase, the last
round of the soft shore ecological monitoring was completed in September 2025.
Site inspections were carried out on a weekly basis with the Contractor and ER to monitor the implementation of proper environmental pollution control and mitigation measures for air quality, noise, water quality, waste management, landscape and visual impacts and preservation and/or transplantation of plant species of conservation importance under the Project. In the reporting period, five (5) site inspections were carried out on 2, 8, 15, 22 and 29 July 2026 for Contract 2, five (5) site inspections were carried out on 3, 10, 17, 22 and 31 July 2026 for Contract 3 and four (4) site inspections were carried out on 9, 14, 21 and 28 July 2026 for Contract 7.
Key observations during the site inspections are summarized in Table 2.7.
Table 2.7 Key Observations Identified during the Site Inspection in this Reporting Month
|
Contract No. |
Inspection Date |
Environmental Observations |
Recommendations/ Remarks |
|
Contract 2 |
2
July 2026 |
Portion 3 •
Accumulated
refuse was observed. |
Portion
3 •
The
Contractor was reminded to remove the refuse in a timely manner and maintain
good housekeeping. |
|
8 July 2026 |
Portion 3 • Mud was observed on public road. |
Portion
3 • The Contractor was urged to clean up the mud and keep the public haul road clean. |
|
|
15 July 2026 |
Portion 3 •
Excessive
runoff was observed. |
Portion
3 •
The
Contractor was urged to provide mitigation measures, rectify the situation
immediately, critically review the drainage plan as to comply with discharge
license and ensure no site runoff or discharge. |
|
|
22 and 29 July
2026 |
Portion
3, 6 •
No
deficiency was observed. |
•
Nil. |
|
|
Contract 3 |
3 July
2026 |
Road
P1 • Poor housekeeping was observed. CUT 3 • Appropriate Non-road Mobile Machinery (NRMM) label was not observed on generator. |
Road P1 • The Contractor was reminded to remove general refuse and maintain good
housekeeping. CUT 3 •
The
Contractor was reminded to affix appropriate NRMM label in accordance with
the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation. |
|
10 July
2026 |
Road
P1, CUT 3 •
Poor
housekeeping was observed. |
Road
P1, CUT 3 •
The
Contractor was reminded to remove general refuse and maintain good
housekeeping. |
|
|
17 July
2026 |
D5 •
Oil
stains were observed on ground. |
D5 •
The
Contractor was urged to clean the oil stain and rectify the situation
immediately. |
|
|
22 July
2026 |
Road P1, D5, SIBC • No deficiency was observed. |
•
Nil. |
|
|
31 July
2026 |
Road P1, D5 •
No
deficiency was observed. |
•
Nil.
|
|
|
Contract
7 |
9
July 2026 |
Portion 31 •
Poor
housekeeping was observed. |
Portion
31 •
The
Contractor was reminded to maintain good housekeeping and remove refuse
regularly. |
|
14 July 2026 |
Portion 30 • Oil drum was observed placing on ground. |
Portion 30 • The Contractor was reminded to provide drip trays for oil drums. |
|
|
21 July 2026 |
Portion 31 •
Appropriate
Non-road Mobile Machinery (NRMM) labels were not observed on excavator. Portion
146 •
Oil
stain was observed on ground. |
Portion
31 •
The
Contractor was reminded to affix appropriate NRMM labels in accordance with
the Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation. Portion
146 •
The
Contractor was urged to clean the oil stain and rectify the situation
immediately. |
|
|
28 July 2026 |
Portion 34, 146 •
No
deficiency was observed. |
•
Nil. |
The Contractors have rectified all of the observations identified during environmental site inspections in the reporting period. The Contractors were reminded to implement all relevant mitigation measures related to construction dust, construction noise, water quality and waste management outlined in the EIA Report and Updated EM&A Manual.
The Contractors of Contract 2, 3 and 7 have registered as chemical waste producer. Sufficient numbers of receptacles were available for general refuse collection and sorting.
All dump trucks engaged on site was equipped with RTTM system during the reporting period. The Surveillance Team of the ET conducted regular site inspection on the dump trucks and their track records. No illegal dumping and landfilling of C&D materials was found during the reporting period.
Wastes
generated during this reporting period include mainly non-inert construction
wastes. Reference has been made to the
waste flow tables prepared by the Contractors.
The quantities of different types of wastes and
imported fill materials are summarised in Table 2.8.
Table 2.8 Quantities
of Different Waste Generated and Imported Fill Materials
|
Contract No. |
Month/Year |
Inert
C&D Materials a (m3) |
Imported
Fill b (sand) (m3) |
Imported
Fill c (public fill) (m3) |
Inert
Construction Waste Re-used d (m3) |
Non-inert Construction Waste
e (m3) |
Recyclable
Materials f (kg) |
Chemical
Wastes (kg) |
|
TCNTE (East) |
1 to 31 May 26 |
408.44 |
0.0 |
0.0 |
6,486.0 |
326.97 |
22,300.0 |
0.0 |
|
1 to 30 Jun 26 |
71.37 |
0.0 |
0.0 |
5,090.0 |
280.81 |
0.0 |
0.0 |
|
|
1 to 31 Jul 26 |
77.78 |
0.0 |
0.0 |
4,055.0 |
269.93 |
0.0 |
0.0 |
Note:
a Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill.
b Imported materials include of sand fill from any source outside of TCNTE.
c Imported sorted public fill include all G200, G400 and glass gullet (local recycling materials) from any source outside of TCNTE.
d Reuse of inert construction waste generated under the TCNTE contracts.
e Non-inert construction wastes include general refuse disposed at landfill.
f Recyclable materials include
metals, paper, cardboard, plastics and others.
Implementation of applicable landscape and visual mitigation measures was monitored in accordance with the Updated EM&A Manual. All measures undertaken by the Contractor during the construction phase and establishment work phase shall be audited by ET to ensure compliance with the intended aims of the measures.
The implementation status of the environmental protection measures is summarized below in Table 2.9. Examples of landscape and visual mitigation measures are presented in Annex J1. The monitoring programme for detailed design, construction and establishment stages is presented in Table 2.10. Event and Action Plan for Landscape and Visual impacts is stated in Annex J2.
Table 2.9 Implementation Status of Landscape and Visual Mitigation Measures
|
Landscape and Visual Mitigation Measures during Construction |
Implementation Status |
Relevant Contract(s) in the
Reporting Period |
|
MM1 – Optimization of
Construction Areas & Providing Temporary Landscape on Temporary
Construction |
Implementation of the
measures were carried out during the detailed design stage of the Project. |
NA |
|
MM2 – Minimize
Topographical Changes |
Implementation of the
measures were carried out during the detailed design stage of the Project. |
NA |
|
MM3 – Preservation of
Potentially Registerable OVTs, Rare and Protective Vegetation |
Tree Protection
Specifications were provided in the relevant Contract Specifications
respectively for implementation by the Contractors under the Project. The Contractors submitted
Detailed Preservation and/or Translocation Plan for Plant Species of
Conservation Importance under EP condition 2.21. The Contractors’
performance on the implementation of the tree maintenance and protection
measures were observed and checked by the ET weekly
during construction period. |
All works contracts |
|
MM4 – Transplanting of
Existing Trees |
Tree Transplanting
Specifications were provided in the relevant Contract Specifications
respectively for implementation by the Contractors under the Project where
trees would unavoidably be affected by the construction works. The Contractors submitted
Detailed Preservation and/or Translocation Plan for Plant Species of
Conservation Importance under EP condition 2.21. The transplanted plant
species of conservation importance were both certified as dead trees by the
QP on 15 June 2022 as no living signs were observed. |
Contract 2 |
|
MM5 – Screen Hoarding |
All works contracts |
|
|
MM6 – Adopting Non-dredge
Method for the Reclamation |
Not applicable during the
reporting period. |
NA |
|
MM9 – Providing Natural
Rock Material/ Planting for Artificial Seawall |
Rock armour
reused and construction of eco-shoreline (mangrove eco-shoreline, rocky
eco-shoreline and vertical eco-shoreline) in progress. The implementation of mitigation measures
was checked by ET during weekly site inspection. Implementation of the measures by
Contractors was observed. |
Contract 3 |
|
MM10 – Compensatory
Planting |
Not applicable during the
reporting period. |
NA |
|
MM11 – Woodland Restoration |
The implementation of
mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by
Contractors was observed. |
Contract 3 |
|
MM12 – Screen Planting |
Not applicable during the
reporting period. |
NA |
|
MM13 – Roadside Planting |
The implementation of
mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by
Contractors was observed. |
All works contracts |
|
MM14 – Aesthetic Design of
Built Development |
The implementation of
mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by
Contractors was observed. |
All works contracts |
|
MM15 – Maximise
Greening on Structures |
The implementation of
mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by
Contractors was observed. |
All works contracts |
|
MM16 – Noise Barrier Design |
Not applicable during the
reporting period. |
NA |
|
MM18 – Landscaping on
Slopes |
Not applicable during the
reporting period. |
NA |
|
MM20 – Lighting Control |
The implementation of
mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by
Contractors was observed. |
All works contracts |
Table 2.10 Monitoring Programme for Landscape and Visual
|
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
|
Design |
Monitoring of design works against the recommendations of the landscape and visual impact assessments within the EIA should be undertaken by the Engineer and Landscape Architect, to ensure that they fulfil the intentions of the mitigation measures. Any changes to the design, including design changes on site should also be checked |
Report by CEDD / ER confirming that the design conforms to requirements of EP. |
Approval by Project Proponent |
At completion of design stage |
|
Construction |
Monitoring of the contractor’s operations during the construction period. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Monthly |
|
Establishment Works |
Monitoring of the planting works during the 24-months Establishment Period after completion of the construction works. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Bi-monthly |
A summary of the Environmental Mitigation Implementation Schedule is presented in Annex B. The necessary mitigation measures were implemented properly for the Project.
There was no notification of summons or prosecution recorded in the
reporting period.
No environmental complaint was received in the reporting period.
Statistics on complaints, notifications of summons, successful prosecutions are summarised in Annex K.
Works to be undertaken in the next monitoring period of August 2026 are summarized in Table 3.1 below, together with the key issues and the key mitigation measures:
Table 3.1 Major Activities for the Next Reporting Period
|
Activities |
Key Issues |
Key Mitigation Measures |
|
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
|
Land-based Works |
||
|
· Slope works, road and drain works for SWSR at Portion 3 · Remedial and Outstanding Works of SWSR at Portion 3 · Overall CCTV survey on new laid watermain |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
|
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major
Infrastructure Works in Tung Chung East (Contract 3) |
||
|
Land-based Works |
||
|
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1
and 3 structure · UU laying works in CUT 1,2,3 · Back-filling works for CUT 2 · Construction works and furniture
installation of PM office at WA9 · Construction works of Contractor
office at WA6 · Drainage, Sewerage and watermain
works at Road L5, L7, L8, L9, D4 and D5 and Portion 16 · DCS works at Road L5, D4 and L7. · Pipe laying works for twin rising
mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works
at Ying Tung Road · Pipe jacking works at Yi Tung Road · Backfilling works for noise
barrier at Portion 11 · Road and drainage works in Road P1 · Road works in Road L3, L4 and L5 · Road widening works at Ying Hei
Road · ELS for SIBC construction · Construction for BC3 at Portion
22B · Pipe pile installation at underpass D1 |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management |
|
Contract No.
NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
|
Land-based Works |
||
|
· Final pressure test for rising mains and 600SW at Portion 146-1 to 146-11 · Road and Drainage works , street furniture at SR-A1 to A5 at Portion 31 · Drainages works at Portion 146-3 · Smart lamp poles ducting laying and footings at Road P1 footpath at 146-3,146-4 146-7 and 146-11, 146-12 · Formation for Road P1 footpath and cycle track at 146-3, 146-4, and 146-11 · Irrigation pipes at P1 road · Smart Lamp poles at P1 road · Backfilling soil mix at P1 road dwarf wall · Pak Mong Bridge insitu deck and furniture · Roads reinstatement at Portion 32 Depot section · RC works and drainage works at SR6 eastbound near Wall D · Parapet Transition construction at RW-R7, A1 and A2 · Parapet construction RW-R5 and Wall D Bay · Road works at Bridge C and Approaching Box Structures · Earthworks casting yard A2 · Asphalt paving, kerbs and concrete profile barriers installation for Road P1 at 146-2, 146-3 · Site clearance within site boundary |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works
|
The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures. The ET will also recommend to the Contractors about the environmental toolbox topics on the abovementioned key issues for the next reporting period.
The tentative schedules for environmental monitoring in August 2026 are provided in Annex L.
This EM&A
Report presents the findings of the EM&A activities undertaken for the TCE
Project during the period from 1 to 31 July 2026 in accordance with the Updated
EM&A Manual and the requirements of the Environmental Permit (EP-519/2016). The environmental monitoring, site
inspection, environmental complaint handling and EM&A reporting in the
works area in Area 113 occupied by MTRC will be covered by EM&A programme of TUE and carried out by existing ET and IEC of
TUE.
Air quality (1-hour TSP), noise and
in-situ preserved plant species of conservation importance were carried out in
the reporting period.
The monitoring results for air quality
monitoring (1-hour TSP) complied with the Action/ Limit
levels in the reporting period.
No exceedance of Action/Limit Level was
recorded for construction noise monitoring in the reporting period.
Mangrove eco-shoreline, rocky
eco-shoreline and vertical eco-shoreline were completed. Eco-shoreline monitoring was scheduled during
the reporting period.
The post-construction soft
shore ecological monitoring has been conducted for 2 years since the completion
of construction. As no significant
changes in density or the distribution pattern of horseshoe crab, seagrass and
intertidal soft shore communities were observed throughout the construction and
post-construction phase, the last round of the soft shore ecological monitoring
was completed.
No post-planting
monitoring of the compensation woodland was carried out in the reporting month.
Monitoring of the in-situ preserved
plant species of conservation importance was carried out in the reporting
period.
Environmental site inspections were carried out during the
reporting period. Recommendations on
remedial actions were given to the Contractors for the
deficiencies identified during the site inspections.
There were no notification of
summons or prosecution recorded in the reporting period. No environmental complaint was received in
the reporting period.
The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.
([1]) ERM (2018a). Updated Environmental Monitoring and Audit Manual for Tung Chung New Town Extension. Deposited to EPD under EP-519/2016
([2]) Arup (2015). Environmental Impact Assessment Report for Tung Chung New Town Extension. Deposited to EPD under Register No. AEIAR-196/2016
([3]) Impact monitoring at monitoring station NMS-CA-1A commenced on 19 September 2018 in view of the close vicinity of the construction works near the residential area at Century Link.