Construction Works Schedule and Location Plans for Tung Chung New Town Extension (EP No. EP-519/2016)


January 2021

  1. Project Description


    The development of Tung Chung New Town Extension (TCNTE), comprising Tung Chung East (TCE) and Tung Chung West (TCW), is a mega-scale and complex project aiming to provide land to meet the future housing economic and social development needs of Hong Kong. Due to the fact that the proposed works are geographically separated, the implementation of mega-scale Project is divided into two packages, namely TCE and TCW respectively. In accordance with the tight delivery programme, the Project will be implemented in phases under separate contracts for the developments of TCE and TCW.


  2. Scope of Works for Tung Chung New Town Extension


    The Tung Chung New Town Extension project (the Project) comprises the following elements:


    1. reclamation of the seabed by a non-dredged method at TCE to form a total of about 130 hectares of land;

    2. construction of about 4.9 kilometers of seawalls, with an eco-shoreline , three drainage box culvert outfalls, three circulation drains and a seawater intake at TCE;

    3. provision of infrastructure for Tung Chung Area 58, including construction of a single two-lane road with a footpath and the associated utility works;

    4. site formation works at TCW;

    5. construction of the River Park including a visitor centre at TCW;

    6. construction of proposed open space;

    7. construction of sustainable urban drainage systems at TCW;

    8. construction of roads, footpaths, cycle tracks and the associated junction / road improvement works;

    9. engineering infrastructure works covering drainage, sewerage, waterworks (including a fresh water service reservoir, a salt water service reservoir and a salt water pumping station), common utility tunnels and landscaping works; and

    10. implementation of environmental mitigation measures and environmental monitoring and audit programme for the works.


    1

  3. Implementation Programme


    The Contract No NL/2017/03 – Tung Chung New Town Extension – Reclamation and Advance Works (i.e. Contract 1) at TCE has been awarded in December 2017 and is scheduled for completion in end 2023. The main contractor for Contract No. NL/2017/03 is Build King – Samsung C&T Joint Venture (BKSCTJV).


    The detailed design for the first phase of site formation and infrastructure works at TCE and TCW (First Phase development) has been completed, while the detailed design for the remaining phase of site formation and infrastructures works is in progress. CEDD will seek funding from the Legislative Council in phases to tie in with population intakes. The construction works at TCE and TCW for the First Phase development will commence in phases once funding approvals by the Legislative Council Finance Committee.


  4. Submission under EP


In view that only the reclamation and advance works contract (i.e. Contract 1) at TCE has commenced, this submission is prepared based on the latest information of Contract 1. The submission shall be updated before commencement of construction of the respective contracts for the site formation and infrastructure works at TCE and TCW according to the relevant requirements contained in the EM&A Manual, EIA Report and EP.


The details of Construction Works Schedule and Location Plans for Contract 1 are provided in Section 1 below.


The layout plan for the site formation and infrastructure works of TCNTE is provided in Section 2.


2


Section 1

Construction Works Schedule and Location Plans for Contract No. NL/2017/03

Tung Chung New Town Extension – Reclamation and Advance Works

image

Black & Veatch Hong Kong Limited

43/F, AIA Kowloon Tower, 100 How Ming Street, Kwun Tong, Hong Kong

博威工程顧問有限公司香港九龍觀塘巧明 街 100 號友邦九龍大樓 43 Tel 電話 +852 2601 1000 • Fax 傳真 +852 2601 3988

Email 電郵 bvhk@bv.com


OUR REF 198377-0297

YOUR REF


DATE 28 January 2021


Sustainable Lantau Office

Civil Engineering and Development Department 13/F, North Point Government Offices

333 Java Road, North Point Hong Kong


For the attention of Mr. S.K. LO / Mr. K.T. WO


Dear Sir,


Agreement No. CE 59/2017 (EP)

Independent Environmental Checker for Tung Chung New Town Extension – Investigation Construction Works Schedule and Location Plans (EP condition 2.12)


We refer to the Construction Works Schedule and Location Plans (Revision 2) dated 12 January 2021 and certified by the Environmental Team Leader on 27 January 2021. Please note we have no adverse comments on the captioned submission. The captioned submission is hereby verified in accordance with the requirement stipulated in Condition 2.12 of EP-519/2016.


Should you have any query, please feel free to contact the undersigned at 2608 7314 (chuawo@bv.com) or our Ivan Ting at 9222 9490 (iec.tcnte@gmail.com)


Yours faithfully,

for and on behalf of

BLACK & VEATCH HONG KONG LIMITED


image

MANUEL CHUA

INDEPENDENT ENVIRONMENTAL CHECKER


    1. ET Leader – ERM (Attn: Mr. Jovy Tam) [by Email: jovy.tam@erm.com]

      Project Manager / TCE – AECOM (Attn: Mr. Chris Cheung) [by Email: sreg1@tce- aecom.com]



      image image image

      image


      Tung Chung New Town Extension


      Environmental Certification Sheet for Environmental Permit No. EP-519/2016


      image

      Document/Plan to be Certified:

      Construction Works Schedule and Location Plans

      (Revision 2)

      Date of Report:

      12 January 2021

      Reference Document/Plan


      image

      Environmental Permit Condition:

      Condition 2.12

      The Permit Holder shall, no later than 3 months before the commencement of construction of the Project, deposit 3 hard copies and 1 electronic copy of a work plan (The Plan) with the Director. The Plan shall include at least the following information/specifications:

      1. a detailed phasing programme of all construction works including reclamation, seawall construction, roadworks, river park and sewage pumping stations of the Project; and

      2. location plan of all construction works in an appropriate scale.

      Reference EP Condition


      image

      image

      ET Certification


      I hereby certify that the above referenced document/plan complies with the above referenced condition of EP-519/2016


      Jovy Tam

      Environmental Team Leader ERM-Hong Kong, Limited

      Date: 27 January 2021

      image

      image

      Contract No. NL/2017/03

      Tung Chung New Town Extension – Reclamation and Advance Works

      Construction Works Schedule and Location Plans                                                                                                        


      Revision Summary


      Revision Number

      Date of Report

      Amendment

      1

      14 May 2018

      First submission

      2

      12 January 2021

      Updated the Location Plans to reflect the latest arrangement.

      Updated Section 2.




      image

      Contract No. NL/2017/03

      Tung Chung New Town Extension – Reclamation and Advance Works

      Construction Works Schedule and Location Plans                                                                                                        


      Contents

      1. Working Programme for Marine Work (Reclamation and Seawall Construction) and Location Plan of the Works

      2. Construction Sequence of Reclamation Works

image

Contract No. NL/2017/03

Tung Chung New Town Extension – Reclamation and Advance Works

Construction Works Schedule and Location Plans                                                                                                        


image

image

Contract No. NL/2017/03

Tung Chung New Town Extension – Reclamation and Advance Works

Construction Works Schedule and Location Plans                                                                                                        


image

image

Contract No. NL/2017/03

Tung Chung New Town Extension – Reclamation and Advance Works

Construction Works Schedule and Location Plans                                                                                                        


image

image

Contract No. NL/2017/03

Tung Chung New Town Extension – Reclamation and Advance Works

Construction Works Schedule and Location Plans                                                                                                        


image

image

Contract No. NL/2017/03

Tung Chung New Town Extension – Reclamation and Advance Works

Construction Works Schedule and Location Plans                                                                                                        

image


Section 2 Layout Plan for

the Site Formation and Infrastructure Works of Tung Chung New Town Extension

image